ICM · Research & Decision Studio · delivery-atlas · Model 1.1.1 · Illustrative inputs

Execution scheduling

Delivery atlas

Expose precedence, schedule float and the assumptions behind a completion estimate.

Model 1.1.1 · Illustrative inputs

Method and assumptions
Delivery / dependenciesIllustrative composition
An illustrative dependency construction. It shows why relationships matter, without portraying a real programme or schedule.

The interactive model requires JavaScript. This saved default illustration remains readable if the runtime is unavailable. Values are computed from the canonical model at build time; they describe fictional inputs, with full calculation precision.

ICM · Delivery atlas · Model 1.1.1 · Default illustrative record

Default illustrative result

The dependency schedule takes 35 weeks under PERT means. 1 critical path has no total float. The first displayed path contains 5 activities and has a 2.69% selected-path deadline approximation for week 30; this does not quantify full-DAG deadline confidence.

Default result metrics
MetricValueUnitCalculation boundary
Expected CPM duration35weeks
Critical activities5
Selected-path deadline approximation2.6898089406839745%Normal approximation for the first displayed path, not full-DAG completion probability.
Selected-path standard deviation2.592724864350674weeks
CPM and PERT schedule
IDActivityPredecessorsPERT durationweeksVarianceweeks²Earliest startweekEarliest finishweekLatest startweekLatest finishweekTotal floatweeksCritical
AScope and design4.3333333333333330.444444444444444404.33333333333333304.3333333333333330Yes
BPermitsA9.6666666666666662.77777777777777774.333333333333333144.333333333333333140Yes
CProcurementA7.33333333333333314.33333333333333311.66666666666666618.16666666666666825.513.833333333333334No
DCivil worksB11.52.251425.51425.50Yes
EInstallationC, D6.333333333333333125.531.83333333333333225.531.8333333333333320Yes
FCommissioningE3.16666666666666650.2531.8333333333333323531.833333333333332350Yes
Critical path assumptions
PathActivity IDsDurationweeksPath varianceweeks²Deadline approximation
1A → B → D → E → F356.722222222222222Selected path
Whole-schedule duration scenarios
Duration assumptionSchedule durationweeks
optimistic23
expected35
pessimistic55

Inputs behind this result

Current general assumptions
Assumption and unitExact supplied value
Target completion (weeks)30
Delivery activities
Activity IDActivityOptimistic durationweeksMost likely durationweeksPessimistic durationweeksPredecessor IDs, comma separated
AScope and design347
BPermits6916A
CProcurement5711A
DCivil works81117B
EInstallation4610C, D
FCommissioning235E
Download exact default inputs and output

Transparent method

  1. PERT mean = (optimistic + 4 × most likely + pessimistic) / 6. Variance = ((pessimistic − optimistic) / 6)^2.
  2. Forward CPM gives earliest start/finish; backward CPM gives latest start/finish; total float = latest start − earliest start.
  3. Every critical path is a start-to-finish path of zero-float activities with contiguous earliest times. At most 50 are displayed.
  4. Deadline probability uses a normal approximation with variance summed on the first displayed critical path.
  5. PERT means, CPM dates, float and path membership use exact rational arithmetic for canonical decimal inputs. Positive float remains positive at every supported scale.

Limits

  • No resource levelling, calendars, correlated durations, uncertainty simulation or contract completion warranty.
  • Normal approximation ignores competing near-critical paths and path switching. Multiple critical paths make the probability especially limited.
  • Standard deviation and the selected-path normal CDF use numerical approximation. Arithmetic exactness does not remove omitted paths, correlations or uncertainty in duration inputs.
  • Numerical input precision: use zero or absolute values of at least 0.000000001. Smaller nonzero inputs are rejected explicitly.