ICM · Research & Decision Studio · corridor-lab · Model 1.1.0 · Illustrative inputs

Industrial logistics

Corridor lab

Locate the binding stage, expose stranded expansion and price the whole chain.

Model 1.1.0 · Illustrative inputs

Method and assumptions
Corridor / continuityIllustrative composition
An illustrative serial chain: the stages belong to one connected system. Its geometry does not represent an operating project or actual capacity.

The interactive model requires JavaScript. This saved default illustration remains readable if the runtime is unavailable. Values are computed from the canonical model at build time; they describe fictional inputs, with full calculation precision.

ICM · Corridor lab · Model 1.1.0 · Default illustrative record

Default illustrative result

The binding stage is Rail corridor. A 20% expansion of Rail corridor creates the largest tested gain of 0.1 Mt/year. Availability stress changes flow to 10.5 Mt/year and unit cost to 24.76 USD/t.

Default result metrics
MetricValueUnitCalculation boundary
Deliverable throughput11.9Mt/year
Whole-chain cost23.73109243697479USD/tAll stages use the same chain throughput.
Unserved demand0.1Mt/year
Availability stress10.5Mt/yearEach availability falls by 10 percentage points.
Whole-chain operating balance
StageNominalMt/yearEffectiveMt/yearUtilisation%SpareMt/yearStage costUSD/tAnnual costUSDmConstraint
Mine release1816.273.456790123456784.33.57647058823529442.56Spare
Rail corridor1411.9100011.129411764705882132.44Binding
Port stockyard1614.482.638888888888892.54.48067226890756353.32Spare
Vessel loading151299.166666666666670.14.5445378151260554.080000000000005Spare
Single-stage 20% capacity expansion
Expanded stageNew effective capacityMt/yearChain flowMt/yearFlow gainMt/yearNext constraint
Mine release19.4411.90Rail corridor
Rail corridor14.28120.1Demand
Port stockyard17.2811.90Rail corridor
Vessel loading14.411.90Rail corridor

Inputs behind this result

Current general assumptions
Assumption and unitExact supplied value
Annual demand (Mt per year)12
Serial stages
StageNominal capacityMt/yearAvailability%Variable costUSD/tAnnual fixed costUSDm
Mine release18902.414
Rail corridor14857.642
Port stockyard16902.820
Vessel loading15803.216
Download exact default inputs and output

Transparent method

  1. Effective stage capacity = nominal capacity × availability.
  2. Serial throughput = minimum of demand and effective stage capacities.
  3. Chain unit cost = sum of variable cost + sum of annual fixed cost / actual annual throughput. USDm divided by Mt gives USD/t.
  4. Each expansion case increases one nominal capacity by 20%; availability stress reduces every stage by 10 percentage points.
  5. Capacity products, throughput, demand gaps and constraint membership use exact rational arithmetic for each canonical decimal input; plotted quantities and costs use numeric approximations.

Limits

  • Steady-state serial system, with no routing alternatives, queues, seasonality, dispatch or inventory simulation.
  • Availability and cost values are user assumptions. No geographic or actual operating project is represented.
  • Exactness applies to the supplied canonical decimal values, not their empirical accuracy. Annual cost and display calculations retain floating-point precision.
  • Numerical input precision: use zero or absolute values of at least 0.000000001. Smaller nonzero inputs are rejected explicitly.