Research replication

The anatomy of delivery

Open the exact fictional inputs behind each worked study. Project cases use their companion model; auxiliary cash bridges retain a separate, verifiable calculation.

Return to the paper

These are illustrative scenarios, not actual project or supplier data. Inputs and method boundaries govern each result.

Illustrative study

Illustrative parallel delivery network

Establish forward/backward dates, float and the selected critical path.

What changes

  • Changed: None; authored reference fixture
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative serialised receiving release

Show a dependency revision changing completion while durations remain unchanged.

What changes

  • Changed: Receiving works now follows equipment readiness rather than design alone
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative supply duration improvement

Shorten the original critical branch and expose the receiving branch as critical.

What changes

  • Changed: Equipment readiness duration estimates only
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative explicit interface decision

Insert a previously omitted release activity and reveal the consequence for downstream completion.

What changes

  • Changed: Added readiness decision after assembly and before integrated testing
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative equal critical branches

Show why one selected-path approximation omits parallel-path uncertainty.

What changes

  • Changed: Receiving duration distribution assumptions equal supply assumptions
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative earlier target only

Change the selected-path deadline reading without changing the dependency schedule.

What changes

  • Changed: Target completion only; no task or dependency changes
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative deterministic task durations

Test the zero-variance conditional deadline boundary.

What changes

  • Changed: Each task estimate is fixed at its base most-likely duration; target matches schedule duration
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative zero-duration release milestone

Preserve a discrete readiness event without adding elapsed duration.

What changes

  • Changed: A zero-duration root milestone is added as the design predecessor
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

Illustrative bounded critical-path display

Test total critical-path counting separately from the bounded displayed list.

What changes

  • Changed: An explicit equal-branch network replaces the base topology; all task durations are deterministic
  • Held constant: Every other input retained from the expressly fictional base unless the named fixture declares a different network
  • Comparison: Full slate tests serialisation, duration and critical-path switching, inserted interface decision, tied branches, target change and deterministic boundaries.

Limits of the study

  • Illustrative finish-to-start DAG with a continuous week basis, no resources, calendars, lags, lead relationships or rework loop.
  • PERT means and variance are assumptions; the selected-path normal deadline approximation is not full-graph completion probability, empirical likelihood or guaranteed delivery.
Open this case in the model

Illustrative study

A short independent activity does not become critical

Keep a supported small positive float distinct from zero when choosing a critical path.

What changes

  • Change: Rescale all durations and deadline together.
  • Held constant: Two independent deterministic tasks.
  • Interpretation: The longer task remains the sole critical path; no stochastic duration distribution is estimated.

Limits of the study

  • Artificial durations diagnose arithmetic and do not represent a practical calendar.
  • Zero task ranges make this diagnostic deterministic; the general app still omits path switching and duration correlation.
Open this case in the model

Illustrative study

Two equal canonical decimal path totals

Reproduce exact equality of the supplied decimal0.1 plus0.2 path and the decimal0.3 direct path.

What changes

  • Change: Raise only the direct task duration by0.000000001.
  • Held constant: Task A, task B and the target deadline.
  • Interpretation: The direct path then becomes strictly longer rather than remaining tied by a tolerance.

Limits of the study

  • The equality is conditional on canonical input values, not duration measurement certainty.
  • The first displayed path remains a selected-path diagnostic, even when several critical paths exist.
Open this case in the model